Main Street Improvements

Project Timeline

Project time line is approximate and subject to change.

Phase 1HWY 34 to 4th Street8/10/2020 - 10/30/2020
Phase 24th Street to 5th Street10/2/2020 - 12/1/2020
Phase 35th Street to 7th Street10/23/2020 - 12/31/2021
Phase 4Railway Street to HWY 3412/3/2020 - 2/10/2021
Bridge 1Mill Race Bridge Removal9/8/2020 - 9/29/2020
Bridge 2Republican River Bridge Replacement9/30/2020 - 12/17/2020

Important Dates

  • Notice of Award – July 15, 2020
  • Preconstruction Meeting—July 28, 2020
  • Notice to Proceed – August 3, 2020
  • Pre-construction Review (Public Meeting) –  August 6, 2020
  • Construction Begins – August 10, 2020
  • 240 Day Total Construction Timeline

Project elements

  • Underground water lines: 8” lines, fire hydrants, and service lines.
  • Underground storm drainage lines and storm inlets.
  • Box culverts on mill race and river
  • Underground electrical lines and conduit: street lighting and misc. electric circuit
  • Curb and gutter.
  • Sidewalks / ADA compliant intersections
  • Replacement of concrete on streets. Street will be widened to better accommodate parking.

Project Success Factors

  • Enhancement of critical main street infrastructure.
  • Clear expectations and communications with businesses and residents.
  • Minimize disturbance to residents and businesses.
  • Finish construction within proposed timeline and budget.

Main Street Completion

Main Street Plans_Overview Opens in new windowMain Street_Pre Constrcution Review InviteMain Street_Project Overview-page-001Main Street75% Design Review Invitation

City Council Work Session Invite

June 2018_Main Street Update
April 2018_Main Street Informtion